Lunes, Marso 13, 2017

Mersey Gateway bridge deck is more than 50% complete

Mersey Gateway milestone reached with over half of the new main bridge deck in place over the River Mersey.

The Mersey Gateway project has passed a significant milestone, with 50% of the project now complete.

Work to install stay cables on the main bridge also passed a key point (Thursday, March 9), on the south pylon.

When complete 146 stay cables will support Halton’s new 1,000-metre long reinforced concrete bridge, with a combined load-bearing weight of more than 53,000 tonnes.

Gareth Stuart, Project Director of the Merseylink construction joint venture, said: “These are two massive achievements for the project.

“The deck and the cables are integral to the design of the Mersey Gateway bridge, and will make it instantly recognisable as one of the most impressive looking crossings in the UK.

“We’re now more than 50% through this highly visual phase of the Mersey Gateway construction, where people will be able to see the stay cables connected to the bridge deck as it emerges across the river week by week.”

Every single strand needs to be installed individually.

Merseylink’s Design Manager, George Moir, said:  “It’s gone well so far, and we’re installing around 6 stays per week from the three pylons.

“The first two strands are threaded through the stay pipe then the tower crane lifts the pipe up to the anchor point in the upper pylon where the top ends of the strands are fixed into place.

“The bottom ends of the strands are then attached to the anchor point in the bridge deck and stressed using a hydraulic system. This enables us to get the correct level of tension needed to support that segment of bridge deck.

“We then use a winch system through the stay pipe to winch the remaining strands up one by one. Once all of the strands have been installed they sit in parallel inside the stay pipe to form the stay cable.”

Counsellor, Rob Polhill, Leader of Halton Borough Council, said: “It’s been fascinating to watch the works in the estuary progress, and we’re now set to see truly incredible scenes as our new bridge enters its final phases of construction.

“Every day the landscape of Halton is changing and I would encourage everyone to catch a glimpse of the work in progress.”

If you would like to read more articles like this then please click here

 

The post Mersey Gateway bridge deck is more than 50% complete appeared first on UK Construction Online.


Walang komento:

Mag-post ng isang Komento